Two updates to recent messages. Thanks Monica…

1.  Change of location Joint Altadena Town Council and PUSD School Board Meeting
        Tuesday, December 4, 2007 @ 7 p.m., Eliot Middle School Auditorium

2.  Change to Pasadena Now article regarding Christmas Tree Lane and repaving of Altadena Drive between Lake and Santa Rosa

         http://www.pasadenalivingmagazine.com/_ArticleManager/publish/article_3446.shtml

        Mike Antonovich’s field representative, Sussy Nemer, sends more specifics:

                  A contractor to the County of Los Angeles Department of Public Works is currently re-constructing this section of Altadena Drive between Santa Rosa Avenue and Lake Avenue. This work involves re-construction of the roadway and improvements to medians, curbs, gutters, and sidewalks.

Given concerns about how the Altadena Drive construction may impact visitors to Christmas Tree Lane, Supervisor Antonovich directed the Department of Public Works to implement the following measures:

  1. No construction will occur on weekends.
  2. Beginning on Friday, December 7th, and lasting through the beginning of January, all construction Monday through Friday will be finished no later than 5:00 p.m.
  3. All driving lanes east-bound and west-bound will be open by 5:00 p.m.
  4. Temporary lane closures will occur during the day Monday through Friday.


By adjusting the contractor’s schedule, Altadenans can rest assured that the construction along Altadena Drive will not impede visitors coming to see Christmas Tree Lane. Traveling to and from Christmas Tree Lane will remain accessible for the thousands of Altadenans and others who come to enjoy this annual celebration.
 